Amena Bakr (Kpler) — Mine Clearance Timeline via PBS NewsHour

Source: PBS NewsHour — June 15, 2026
Key voice: Amena Bakr, Head of Middle East, Kpler

The Recovery Timeline

Kpler's Amena Bakr provided the most specific physical-clearance breakdown available:

Phase Duration
Mine clearing operations Up to 6 months
Vessels leaving and returning to reload 2-3 months
Restarting production to pre-war levels Additional 3 months
Total ~11+ months from deal

Implications

The mine-clearing timeline is the most cited bottleneck. Even with a ceasefire deal signed June 19, the physical infrastructure of recovery has a minimum ~11-month ramp.

This means structural supply disruption persists well into 2027 regardless of political deal quality — production restart in Iraq, Kuwait, Iran itself all face independent timeline constraints beyond the shipping clearance.

Bakr's specificity on this point anchors the "2027 is the real recovery year" narrative now appearing across multiple sources (Rystad, Capital Economics, ICIS in the Guardian piece).

Concepts

  • phased-restart-protocol — 6 months mine clearing + 2-3 months reload + 3 months production restart = structural disruption well into 2027

Ingested 2026-06-18. Source: PBS NewsHour / Kpler.